17th December 2018
Dr. Suhat Korkmaz, CEO of Tosyali Holding, recently announced completion of the state-of-the-art direct reduction ironmaking plant capable of simultaneous production of hot and cold direct reduced iron (HDRI and CDRI), which will feed the electric arc furnace (EAF) melt shop of a new Tosyali Algeria iron and steel facility. The announcement followed a site visit by Youcef Yousfi, Algeria Minister of Industry and Mining, hosted by Fuat Tosyali, Chairman of Tosyali Holding.
The 2.5 million tons/per year plant was supplied by Midrex Technologies, Inc. and its consortium partner, Paul Wurth.
“The MIDREX® DRI combination plant provides Tosyali Algeria greater flexibility in producing high quality steel products,” Dr. Suhat said, “and will eliminate the need to purchase imported scrap.”
Commissioning of the plant began in July 2018, and production of cold DRI (CDRI) started in late November 2018. Hot DRI (HDRI) production is expected to begin in February 2019, which also is the scheduled official plant start-up.
History of Tosyali Holding
Founded in Iskenderun, Turkey, in 1952, Tosyali Holding now has a total of 18 facilities on three continents in six different regions along with 12 affiliates. Tosyali Holding includes three production companies – Tosçelik Profil ve Sac Endüstrisi A.Ş., Tosyali Demir Çelik Sanayi A. Ş., and Tosçelik Granul San, A. Ş. – all of which are leaders in their sectors, and Tosyali Diş Ticaret A. Ş., which conducts foreign trade for the group.
For more information, please visit en.tosyaliholding.com.tr/.
Midrex Technologies, Inc.
For more than 45 years, Midrex Technologies, Inc. has been the leading innovator and supplier of direct reduction ironmaking technology. Plants based on the MIDREX NG™ Process each year produce more than 60% of the entire world’s supply of DRI and more than 80% of DRI produced by shaft furnace technologies.
MIDREX NG™ Plants are known for their reliability, flexibility, and hours of continuous operation, often well beyond industry standards. Several MIDREX® Plants built almost 50 years ago exceeded their original design capacities and product quality specifications in 2017. MIDREX® Plants can be turned down with no significant economic impact during difficult market conditions and returned to full production quickly and efficiently.
For more information, please visit www.midrex.com.
32, rue d'Alsace
L-1122 Luxembourg
LUXEMBOURG
P.O. Box 2233
L-1022 Luxembourg
LUXEMBOURG
Tel.: (+352) 4970-1
Fax.: (+352) 4970-2209
2024 © Paul Wurth - All rights reserved - Disclaimer - Contact